Star
Awards Program
The Star Award represents a symbol of excellence,
and someone or something designated a star are thought
to be pre-eminent. The award program is to recognize
and promote professionalism and excellence in "star
quality" projects.
The Star Award honors the chosen project as the most
outstanding new construction project in the State
of North Carolina, and is selected on the merits and
challenges of the project by an objective group of
judges. The Star Award represents a symbol of excellence
and is the highest achievement in the Design and Construction
industry.
Award nominations are open to all CPN members. There
are two categories for 2007 - one category for projects
under $10 million and one category for projects over
$10 million. The award committee will evaluate each
project and will consider the following:
 |
Project's outcome |
 |
Owner's Satisfaction |
 |
Overall project management |
 |
Safety |
 |
Quality management |
 |
Cost management |
 |
Schedule management |
 |
Project complexity |
 |
Cooperative Team Effort |
 |
Innovation and creativity |
The CPN award committee will acknowledge completed projects
that meet the following criteria:
 |
The project must be located in North
Carolina and substantially completed (have certificate
of occupancy) by December 31, 2007 |
 |
The project must be unique in its concept and
successful in its completion schedule, within
budget and of the desired "star" quality.
|
 |
At least two (2) CPN members must have played
a significant role in the areas of planning, financing,
design, management or construction. More than
two members are desirable. |
 |
The project must standout from others being
considered; it must have "star quality".
|
The award presentation will be at our 2008 Annual
Conference being held at The Homestead, Hot Springs,
VA April 11-13, 2008. If you have questions,
don't hesitate to call Mark Morgan at (336) 478-2267.
Please provide the following information when submitting
your nomination:
 |
CPN Star Award Nomination Form (6
copies) |
 |
Letter from each CPN member
stating what role they played |
 |
Letter from owner or end user describing why the project was a success and their overall satisfaction |
 |
Detailed pictures of the completed project and cd with pictures in digital form. |
| To:
(mail)
|
CPN Starr Award Program
Attn: Mark Morgan
c/o Weaver Cooke Construction, LLC
8401 Key Boulevard
Greensboro, NC 27409 |
| (FedEx) |
Weaver Cooke Construction
8401 Key Boulevard
Greensboro, NC 27409 |
2006
Star Award Winners
Explore the Wild -
NC Museum of Life and Science
Durham, NC
(Under $10M Project Winner)
This project involved virtually the re-building
of wetlands to recreate a waterfowl environment
in an abandoned rock quarry that is a part of the
Museum’s 70-acre campus. All work was carefully
performed to protect the existing wildlife in the
area. The project included constructing a new entrance
into the existing museum, new animal exhibit areas,
manmade rock and water features, over 30,000 SF
of boardwalk and a sailboat pond. The board walk
weaves in and out of the cliffs around to the wetlands
and through the various exhibits. Building in and
around existing animal habitats [bears, wolves,
lemurs] for exhibit purposes made this project very
unique and challenging. Challenges also included
building in an abandoned rock quarry and encountering
mammoth rock, and the numerous changes generated
by the Owner’s ever growing vision for this
learning facility. The Museum remained open the
entire time without losing one single day of operation.
The construction team was focused on providing a
very clean and safe jobsite as visitors were able
to view the entire construction site as a learning
experience.
This project was extremely complex and challenging.
Original budgets were broken down into 18 phases
of the GMP. The project also included constructing
100 customized exhibits to include the new black
bear exhibit (while Ursela the bear was in residence.)
Also included was an expansion to the museum entrance,
the construction of a dinosaur trail, expansion
of the existing parking areas, and the addition
of the Caterpillar Café to the existing museum.
This project also received Carolinas AGC highest
honor, the Pinnacle Award for 2006.
CPN members involved the project team included:
 |
Dave Walters
- New Atlantic Contracting, Inc. |
 |
Leo Segasti - BJAC |
 |
Willie Stewart - Stewart
Engineering |
 |
David Clem - Senn Dunn |
 |
Ronnie White - Duke Power
|
 |
Jay Motsinger - Dixon Hughes
|
 |
Holt Gwyn - Conner Gwyn Schenck |
 |
Jade Osborne - Osborne-Brumsey
& Associates, Inc. |
Client - NC Museum of Life and Science - Roy Griffiths,
VP Exhibits and Planning
Piedmont Town Center
Charlotte, NC
(Over $10M Project Winner)
Piedmont Town Center is a mixed-use project located
on an 11 acre site in the South Park area of Charlotte,
North Carolina. It consists of 2 eight-story pre-cast
office buildings totaling 417,000 square feet (one
serving as the headquarters of Piedmont Natural
Gas), 2 seven-story pre-cast parking decks (each
with 1,000 spaces), 179 condominium units and 95,000
square feet of street level retail space. The project’s
master schedule dictated that Piedmont Natural Gas
Corporate Headquarters building begin first. Foundations
and structure followed on the other five buildings
on a successive three-week stagger. By June, 2005
thirteen cranes were on site to facilitate structural
steel erection, architectural and structural pre-cast
erection and concrete construction activities. Coordinated
communication between the eleven Shelco Superintendents
on site became a premium. Weekly construction meetings
with Superintendents and Project Managers were held
on Mondays to facilitate and coordinate major concrete
pours and deliveries. By mid-August, manpower had
peaked with over 1,000 workers on site.
Two pre-cast parking decks are located on each
side of Piedmont Row Drive. On three sides of each
deck, the ground floor, 2-story retail space and
the 5 levels of residential condominiums are supported
by a post tension concrete structure. The cast-in-place
structure activities were ongoing simultaneously
with the structural pre-cast erection activities.
Only a 2” expansion joint separated these
buildings. Pre-cast hoisting activities and concrete
structure activities had to be coordinated and cycled
daily to avoid potential safety issues associated
with heavy crane lifts in the vicinity of workmen.
Crane lift work areas were flagged and monitored
to ensure the safety of the workmen.
The focal point of the design of this project is
a large 4-way traffic circle bordered by planters,
pre-cast walls, urns, pavers and pre-cast steps.
The center of this circle features a 50’ diameter
fountain with a 30’ high center water jet
and 12 smaller jets. Careful detail during the installation
was necessary due to the compressed schedule so
as not to interfere with the construction of the
exterior skin activities of the adjacent residential
buildings. The heart of Piedmont Town Center is
the central plaza with its roundabout and monumental
fountain. Both office towers and the residential
crescents on their opposite sides focus on the space
and define it. Three nationally known restaurants
open onto the plaza with outdoor dining terraces,
making the space a visually animated, “people
watching” destination.
Piedmont Town Center represents a project incorporating
a myriad of complicated facets. Four different building
types, three different structural systems all integrated
together, a maze of governmental approvals and signoffs,
a limited work area and a nearly impossible schedule
– a unique story in itself.
Piedmont Town Center with its introduction of high
density residential in a highly integrated mixed-use
project in the heart of South Park helps establish
the next direction of South Park’s transformation
into a second urban core for Charlotte.
CPN members involved the project team included:
 |
Howard Peabody
- Shelco, Inc. |
 |
Tommy Almond - LT Mechanical |
 |
Rick Brown - B&B Contracting |
 |
David Hamilton - Hamilton Fay
Moon Stephens Steel & Martin, PLLC |
 |
Mickey Norris - PSI, Inc. |
 |
Ronnie White - Duke Power |
Client – Crescent Resources and Lincoln Harris
(Joint Venture)
Previous
Star Award Winners
| 2005 |
Under
$10M Project:
Addition to Softball Complex; UNC Greensboro
CPN Members: Stewart Engineering, Inc.; New Atlantic
Contracting, Inc.; UNC-Greensboro; Osborne Brumsey
& Associates, Inc.; Conner Gwyn Schenck, PLLC
Over $10M Project:
The Rams Head Center;
UNC Chapel Hill
CPN Members: Stewart Engineering, Inc.; New Atlantic
Contracting, Inc.; Retenbach Constructors; Starr
Electric; Chandler Concrete; David Allen Company,
Inc.; Martin Architectural Products |
| 2004 |
Center
for Interdisciplinary Engineering, Medicine &
Applied Sciences at Duke University
CPN Members: Skanska, David Allen Co.,
Environmental Air Systems, Engineering Specialties
Co. |
| 2003 |
Thomas Built Buses
C2 Plant CPN Members: HICAPS,
Inc., Rentenbach, Calloway Johnson Moore West,
Associated Sprinkler, Starr Electric |
| 2002 |
Grove Arcade Rehabilitation
CPN Members: Tri/Meck Mechanical, Inc.,
Scott Insurance, Calloway Johnson Moore West,
Carolina Power & Light |
| 2002 |
Streets at Southpoint
CPN Members: S&ME, The Mangum Group/C.C.
Mangum Contractors, Facility Consulting Group,
Beers Construction, John R. McAdams Co., David
Allen Co. |
| 2001 |
Digital Optics Project
CPN Members: Shelco, Trigon Engineers,
McCracken & Lopez |
| 2000 |
The Air Borne Special
Forces Museum CPN Members:
HICPAPS, Inc., Conner Gwyn & Schenk, Calloway
Johnson Moore West, Beers/Fowler Jones |
| 2000 |
The Grandover Hotel
& Spa CPN Members: HICAPS,
Inc., Koury Corp., Triad Design, David Allen Co. |
|